In response to a query by the Trust, the M2 Project responds:
The current program is on track for completion of Murray Farm Road Bridge by the summer holiday period in December. The traffic lights will be removed and normal two-way operation of the bridge will be restored for motorists. Please note this is subject to weather and any technical issues which may arise during the final bridgeworks activities to be undertaken over the next two months.
In regard to remediation under Devlins Creek Bridge, the project team is required to reinstate the area to its condition prior to the start of construction. The remediation program is 30% complete, with full reinstatement currently programmed for January 2013.